The Bicentennial Bikeway is being upgraded in stages, from a generally 3.0–3.5 metre wide shared path to a generally 3.5 metre wide dedicated bike path with a separate 2.0 metre wide pedestrian path. Although this will be of great benefit cyclists in the long term, the construction will cause some inconvenience.
The overview map (
PDF, 181 kB) below shows the individual stages.
- Stage one: Cribb Street to Park Road — complete
- Stage two: Lang Parade to Land Street — complete
- Kurilpa Park & Victoria Bridge upgrades — complete
- Hale Street West: Go Between Bridge to Cribb Street — complete
- Hale Street East: William Jolly Bridge to Go Between Bridge — complete
- Stage three: Park Road to Lang Parade — June 2013
- Stage four: Land Street to Landsborough Terrace — Late 2013/early 2014
For more information on the upgrade, see the BCC page or contact the project team:
- Phone: 1800 727 923 (freecall)
- Phone: 07 3403 8888 (after hours)
- Email: bikewayprojects@brisbane.qld.gov.au
- Write to: Bicentennial Bikeway upgrade project,
GPO Box 1434, Brisbane QLD 4001
There is also unrelated work to upgrade the path and improve security along the Northbank (city) section of the bikeway, between QUT and the Victoria Bridge, in four stages:
- Victoria Bridge to Queens Wharf Road — complete
- Queens Wharf Road to QUT ferry terminal — complete
- QUT ferry terminal through Parliament carpark (pedestrian pathway) — complete
- QUT ferry terminal to Goodwill Bridge — complete
Stage one: Cribb Street to Park Road
- Completed: August 2009.
Stage two: Lang Parade to Land Street
- Completed: September 2010.
Kurilpa Park & Victoria Bridge upgrades
- Scheduled: November 2010 –
Aprilmid 2011 - Completed: mid 2011.
- Required to facilitate detours during Hale Street East stage (below)
- Kurilpa Park path (from the end of Riverside Drive to Kurilpa Bridge) closures:
- Closed to cyclists 24 hours
- Closed to pedestrians at night
- Detour along Boundary Street & Montague Road (cyclists on-road)
- Relatively minor changes to the path connections below Victoria Bridge (southern end)
- Correspondence:
- Construction commencement (
PDF, 120 kB), with map (
PDF, 183 kB) (8 Dec 2010) - Construction notification 7–20 Feb 2011 (
PDF, 32 kB) (4 Feb 2011) - Construction notification 7–20 Mar 2011 (
PDF, 37 kB) (4 Mar 2011)
- Construction commencement (
Hale Street West: Go Between Bridge to Cribb Street
- Scheduled: November 2010 –
AprilAugust 2011 - Completed: August 2011.
- Closures:
- Totally closed to cyclists at night (8pm – 5am)
- 3 metre section of path open to cyclists during the day (5am – 8pm), from 6 August
- Two-way flow
- Traffic controllers present
- Minor delays still possible
- Totally closed to pedestrians 24 hours
- Cribb Street underpass totally closed 24 hours
- Detour via footpath on opposite side of Coronation Drive
- Construction updates:
- Construction commencement (
PDF, 169 kB), with map (
PDF, 245 kB) (2 Dec 2010) - Construction 13 – 24 Dec (
PDF, 37 kB) (10 Dec 2010) - Change of access from 10 Jan (
PDF, 316 kB) (6 Jan 2011) - Change of access from 27 Jan (
PDF, 314 kB) (24 Jan 2011) - Construction 7 – 19 Feb (
PDF, 28 kB) (8 Feb 2011) - Construction 28 Feb – 12 Mar (
PDF, 34 kB) (25 Feb 2011) - Construction 14 Mar – 26 Mar (
PDF, 34 kB) (11 Mar 2011) - Construction 28 Mar – 9 Apr (
PDF, 34 kB) (28 Mar 2011) - Construction 11 Apr – 23 Apr (
PDF, 33 kB) (8 Apr 2011) - Construction 25 Apr – 7 May (
PDF, 33 kB) (21 Apr 2011) - Construction 9 May – 21 May (
PDF, 33 kB) (6 May 2011) - Construction 24 May – 4 Jun (
PDF, 34 kB) (20 May 2011) - Construction 6 Jun – 18 Jun (
PDF, 34 kB) (3 Jun 2011) - Construction 20 Jun – 2 Jul (
PDF, 41 kB) (17 Jun 2011) - Construction 4 Jul – 16 Jul (
PDF, 41 kB) (1 Jul 2011) - Construction 18 Jul – 30 Jul (
PDF, 45 kB) (15 Jul 2011) - Construction 1 Aug – 13 Aug (
PDF, 45 kB) (29 Jul 2011) - Construction 15 Aug – 27 Aug (
PDF, 41 kB) (12 Aug 2011)
- Construction commencement (
- Some more information is on BCC’s Hale Street West page
Hale Street East: William Jolly Bridge to Go Between Bridge
- Scheduled:
AprilJune 2011 –Januaryearly 2012 - Completed: December 2011.
- Closed from 15 June 2011:
- Closed to cyclists and pedestrians 24 hours between Go Between Bridge and Makerston Street ramp
- Detour via Go Between Bridge and Kurilpa Bridge, Victoria Bridge or Goodwill Bridge, using the paths upgraded by the earlier Kurilpa Park and related works
- Construction updates:
- Construction 13 Jun – 25 Jun (
PDF, 70 kB) (14 Jun 2011) - Construction 27 Jun – 9 Jul (
PDF, 70 kB) (24 Jun 2011) - Construction 11 Jul – 23 Jul (
PDF, 66 kB) (8 Jul 2011) - Construction 25 Jul – 6 Aug (
PDF, 49 kB) (22 Jul 2011) - Construction 8 Aug – 20 Aug (
PDF, 49 kB) (5 Aug 2011) - Construction 22 Aug – 3 Sep (
PDF, 45 kB) (19 Aug 2011) - Construction 5 Sep – 17 Sep (
PDF, 45 kB) (2 Sep 2011) - Construction 19 Sep – 1 Oct (
PDF, 45 kB) (16 Sep 2011) - Construction 3 Oct – 15 Oct (
PDF, 45 kB) (30 Sep 2011) - Construction 17 Oct – 29 Oct (
PDF, 45 kB) (13 Oct 2011) - Construction 31 Oct – 12 Nov (
PDF, 45 kB) (28 Oct 2011) - Construction 14 Nov – 26 Nov (
PDF, 49 kB) (11 Nov 2011) - Construction 28 Nov – 10 Dec (
PDF, 41 kB) (24 Nov 2011) - Construction 12 Dec – 24 Dec (
PDF, 45 kB) (8 Dec 2011)
- Construction 13 Jun – 25 Jun (
- Some more information is on BCC’s Hale Street East page
Stage three: Park Road to Lang Parade
- Scheduled: current under works – March 2013 – June 2013
- Path has been narrowed down through work site, with only cyclists being able to proceed through. Cyclists are asked to ride with due care with regard to the reduced path width.
Stage four: Land Street to Landsborough Terrace
- Not yet scheduled.
Northbank security upgrades
Between December 2010 and June 2011 the Department of Public Works will be performing works to improve lighting, pathway condition and install security cameras on the Northbank section of the Bicentennial Bikeway, between QUT and the Victoria Bridge. Efforts will be made to minimise disruptions but users can expect some partial and full closures, temporary detours and short term delays.
- Department of Public Works project page
- Project overview (1 Jan 2011) (
PDF, 385 kB) - Flyer (9 Dec 2010) (
PDF, 252 kB)
- Note: the phone number and URL are incorrect
- Frequently asked questions (17 Dec 2010) (
PDF, 541 kB)
For more information please contact the project office on 1800 396 046 or ADCO Constructions on 07 3511 5555.
Victoria Bridge to Queens Wharf Road
- December 2010 – end February 2011
- Partial closure for works and painting.
- Half of area fenced.
- Stop/go control when necessary to move equipment, etc.
Queens Wharf Road to QUT ferry terminal
- February 2011 – April 2011
- Partial closure for works and painting.
- Fencing half of pathway.
- Stop/go conrol when necessary.
QUT ferry terminal through Parliament carpark (pedestrian pathway)
- February 2011 – April 2011
- Full closure.
- Detour pathway through carpark.
QUT ferry terminal to Goodwill Bridge
- February 2011 – May 2011
- Full closure.
- Detour via QUT campus (Gardens Point Road)
- Northbound cyclists on road or footpath
- Southbound cyclists on new contra-flow lane or footpath